Utility Account Brief

San Francisco Public Utilities Commission: Utility Account Brief

A supplier's guide to the San Francisco Public Utilities Commission: how it is organised and makes decisions, its financial position and priorities, how it buys, and the opportunities to target first. SFPUC is buying against a US$12,559.0 million capital plan in which Wastewater takes US$5,916.1 million and Hetch Hetchy Power capital rises 81.6%. Its largest construction package out for bid in October 2026, the Folsom Harrison/Treat box sewers, is estimated at US$200 million to US$240 million after an earlier round drew a single bid.

Geography
San Francisco, California, United States; regional wholesale supply in Alameda, Santa Clara and San Mateo counties
Evidence current to
13 November 2026
Format
PDF
Length
11 pages
Edition
November 2026, First edition
Price
USD 499
Secure Stripe checkout · your paid edition is delivered privately in this browser.

Paste the caption with your link. Social platforms control how previews appear.

01

Executive overview

Key findings

US$12,559.0 million: adopted 10-year capital plan, FY2026-27 to FY2035-36; about 70% debt-funded (plan)

US$5,916.1 million: Wastewater share of the plan, the largest; Hetch Hetchy Power US$2,242.7 million, up 81.6% (plan)

Aa2 / AA- and Aa2 / AA: Water and Wastewater ratings (Moody's / S&P); S&P Wastewater outlook revised to Stable, July 2026

US$200 million to US$240 million: estimated value of the largest construction contract out for bid in October 2026, the Folsom Harrison/Treat box sewers (WW-719CR2)

02

Buyer relevance

Who the report is for

Heavy civil, water main and sewer contractors

Target the open WW-719CR2, WD-2914, WW-796 and WD-2918 bids and the rolling replacement contracts listed into 2027.

Electrical and substation firms

Prepare for the US$495M Spear Street Substation design-build and the US$50M Moccasin Powerhouse upgrades.

Treatment process and equipment suppliers

Reach the US$1,470.3M nutrient removal project through its progressive design-builder and the Oceanside and North Point upgrades.

Engineering, construction management and advisory firms

Track the professional services contracts out for proposal and in development, including a US$12M Municipal Advisory Services contract.

03

Decision scope

Questions answered

01

What is SFPUC's capital budget?

US$12,559.0 million over FY2026-27 to FY2035-36, about 70% debt-funded, with Wastewater at US$5,916.1 million.

02

What is out for bid now?

The October 28, 2026 list includes WW-719CR2 at US$200M–240M and WD-2914 at US$45M–50M, with WD-2914 bids due November 19, 2026.

03

Who already holds SFPUC's largest programs?

MWH/Webcor JV is CM/GC on the US$2,837.1 million Biosolids Digester Facilities, and Clark Construction holds the 2000 Marin and Southeast operations buildings.

04

How does SFPUC procure large projects?

Through public bids, construction manager/general contractor RFQs and progressive or fixed budget limit design-build, with a 30% local hiring minimum on capital projects over US$400,000.

04

Inside the report

Inside the complete report

1. The Account at a Glance

2. Organization and Decision-Making

3. Financial Position

4. Priorities and Pressures

5. How San Francisco Public Utilities Commission Buys

6. Opportunity Register

7. Commercial Priorities: Where to Focus First

8. Watch List: What to Monitor and What to Do

Source Register

05

Public preview

What to watch next

Bid results for WD-2914, WW-796 and WD-2918 (November–December 2026)

Show competition levels on pipeline and sewer work.

WW-719CR2 bid date

Largest construction package currently out for bid.

Spear Street Substation RFQ (earliest January 2027)

US$495M design-build; owner advisor procured first.

General Manager appointment (from December 2026)

New leadership may reorder priorities.

Sample page · page 7 of 11

The Opportunity Register lists open, emerging and confirmed SFPUC projects with stage, value, next milestone and route to market.

Report page with an opportunity register table of SFPUC projects, showing status, stage at November 13, 2026, estimated value, next milestone and how to access.

06

Included

What you receive

The complete PDF report: 11 pages, 9 sections, 7 tables and a register of 16 sources.

This edition

November 2026, First edition.

07

Evidence & method

Evidence and method

Built from SFPUC's contracting opportunities list updated October 28, 2026, its adopted FY2026-27 to FY2035-36 Capital and Financial Plans, quarterly capital program reports to June 2026, Commission agendas, bond and ratings releases and the audited FY2025 financial report.

Sources

16 sources, listed in the report's source register. Evidence current to 13 November 2026. Principal data periods: FY2025 audited results (year ended June 30, 2025); 10-Year Capital and Financial Plans for FY2026-27 to FY2035-36 (adopted February 10, 2026); capital program reports for the quarter ended June 30, 2026; SFPUC contracting opportunities list updated October 28, 2026. Procurement status checked on November 13, 2026. All currency is US dollars..

08

Lead analyst

Robert C. Brears

Founder, Our Future Water Intelligence

Robert C. Brears is a water-security specialist and author whose work examines utility governance, infrastructure investment, climate resilience and long-term water-system change for executive and policy audiences.

  • Decision-focused utility intelligence
  • Published water-policy author
  • Evidence-grounded system analysis

09

Buyer FAQs

Before you purchase

Who can use the report?

Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.

How is the report delivered?

The PDF is available to download immediately after confirmed payment, through our secure delivery system.

Can my organization buy wider access?

Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.

10

San Francisco Public Utilities Commission: Utility Account Brief

Format
PDF
Length
11 pages
Edition
November 2026, First edition
Price
USD 499
Secure Stripe checkout · your paid edition is delivered privately in this browser.

11

Report details

Publication details

Publisher
Our Future Water Intelligence
Report family
Utility Account Brief
Edition
November 2026, First edition
Format
PDF
Length
11 pages
Reference
OFW_EXT_SAN_FRANCISCO_PUBLIC_UTILITIES_COMMISSION_UTILITY_ACCOUNT_BRIEF_8b2073c1f335
Evidence current to
13 November 2026

14

Explore this report family

More Utility Account Briefs

Explore the same report family covering other utilities.

Watercare Services: Utility Account Brief cover

Watercare Services: Utility Account Brief

An assessment of where Watercare Services will spend its NZ$15.2 billion 10-year programme, how it buys, who already holds its major work and where suppliers should focus first. Watercare must lift capital delivery from NZ$959.5 million in FY2026, NZ$90.5 million below target, to a forecast NZ$1,350.0 million in FY2028. Much of its work already sits with standing panels of 19 renewals partners, while the NZ$1.7 billion Waikato Water Supply Programme, opened to alliance bidders on 2 September 2026, is the largest new opening.
Geography
Auckland (Tāmaki Makaurau), New Zealand
Edition
November 2026, First edition
Length
11 pages
Explore report
Acea: Utility Account Brief cover

Acea: Utility Account Brief

A supplier's guide to Acea's water business: where it spends, how it buys through one central portal, who holds its major contracts and which programmes to target first. Acea invested €890.8 million in water in 2025 and buys centrally for its main companies; Acea Ato 2 alone placed about €322 million of orders with 288 suppliers in 2024. Network, leakage, digital and reuse work is backed by a €450 million EIB package for 2027–2030, while the €1.449 billion Peschiera aqueduct is back before the courts after its first award was annulled.
Geography
Rome and ATO 2 Lazio Centrale, Italy
Edition
November 2026, First edition
Length
11 pages
Explore report
Johannesburg Water: Utility Account Brief cover

Johannesburg Water: Utility Account Brief

A commercial brief for suppliers asking where Johannesburg Water spends, how it buys, which projects are open or emerging and where to focus first. Johannesburg Water budgets R13.06 billion of capital for 2026/27 to 2030/31 and had four sewer-main tenders open on 23 November 2026, closing between 27 January and 4 February 2027. It spent 18% of its R1.704 billion capital budget in the first half of 2025/26 and collected 74.84% of billing in FY2024/25, and late payment has delayed contractors on three projects.
Geography
City of Johannesburg, Gauteng, South Africa
Edition
November 2026, First edition
Length
11 pages