An assessment of how Bahrain's Electricity and Water Authority is changing from owning plants to buying private supply and operating the system, and which awards and targets set its path to 2032. Two private reverse osmosis plants in procurement, Hidd at 60 MIGD and Sitra at 30 MIGD, would add capacity equal to 42.2% of EWA's 213.22 MIGD installed in 2024, but neither had been awarded by 24 November 2026. EWA has set a 23% water loss target for 2032 with staged flow-meter replacement from 2026, while its first solar IPP was retendered with operation now targeted for 31 December 2028.